Project Status
|
Proposed Project Description
|
Proposed Implementation Schedule
|
Project Cost
|
Project Image
|
|
Completed
|
Raw Water Intake Project
|
|
|
 |
|
Completed
|
Airport Road Paving
|
|
|
|
|
Ongoing
(Quarter 1 2009)
|
Romeo T. Flores
Park Project--Phase I
|
|
|
 |
| Upcoming |
Zapata County Higher Technology Center
Phase I
(adjacent to Zapata County Community Center)
|
|
|
 |
|
Upcoming
|
Zapata County Boat Ramp Project
Phase I
|
|
|
|
|
Ongoing
|
Zapata County Water Treatment Plant
|
|
|
 |
|
Design & Planning complete; awaits funding
|
Zapata County Higher Technology Center
Phase II
|
The project is planned for a 24 month period
|
$2,000,000
|
|
|
Design & Planning complete; awaits funding
|
Zapata County Museum
(old civic center site)
|
The project is planned for a 12 month period.
|
$3,500,00
County funds available: $1,800,00
|
|
|
Design & Planning complete; awaits funding
|
Zapata County Sewer Improvement
(Texas Water Development Board)
|
The project is planned for a 24 month period.
|
$6,400,000
County Texas Water Development loan
|
|
|
Design & Planning complete; awaits funding
|
Las Palmas Colonia Sewer collection project
|
The project is planned for a 24 month period.
|
$1,700,000
|
|
|
Design & Planning complete; awaits funding
|
School Safety Sidewalk project
Villarreal Elementary & South Elementary
|
The project is planned for a 12 month period.
|
$250,000
|
|
|
Design & Planning complete; awaits funding
|
Storm Drainage
Pct. 4 Park
(to maximize land use and control flooding)
|
The project is planned for an 18 month period.
|
$750,000
|
|
|
Design & Planning complete; awaits funding
|
San Ygnacio
Drainage Project
(project site is in and around the National Historic District--all Texas Historical Commission permits have been acquired.
|
The project is planned for an 18 month period.
|
$1,500,000
|
|
|
Design & Planning complete; awaits funding
|
Flood Prevention in Medina Addition (colonia), as identified in the 2007 Flood Prevention Study
|
The project is planned for a 24 month period.
|
$6,500,000
|
|
|
Design & Planning complete; awaits funding
|
County Boat Ramp Project--Phase II
(completion of presently designed park project--TXDOT administered project
|
This project is planned for a 24 month period.
|
$1,500,000
|
|
|
Design & Planning complete; awaits funding
|
Jennings and Pedernales County Roads (drainage)
|
The project is planned for a 12 month period.
|
$600,000
|
|
|
Design & Planning complete; awaits funding
|
Falcon Meza Colonia Paving Project
|
This project is planned for a 24 month period.
|
$2,300,000
|
|
|
Design & Planning complete; awaits funding
|
Veleño Bridge--utility relocation
(required by Texas Department of Transportation)
|
This project is planned for a 24 month period.
|
$1,800,000
(paid by county)
|
|
|
Design Ready
|
Paving of
Aguilares Road FM 3169
(4.5 miles, from end of payment to county line; all easements are in place)
|
The project is planned for a 24 month period.
|
$5,400,000
|
|
|
Design Ready
|
County Road
Paving Project--
Jennings (10 miles), Pedernales (8 miles),
Los Lobos (6 miles), Tepozan (.38 miles), Meza Salinas (4 miles), Alejandrenas (10 miles)
|
This project is planned for a 48 months period. Work will be done in phases and could start in less than 12 months.
|
$38,380,000
|
|
|
Design Ready
|
Siesta Shore WCID, water distribution system
(renovation of inadequate distribution system, no fire protection)
|
This project is planned for a 24 month period.
|
$7,000,000
|
|
|
Design Ready
|
Sheriff & Fire Department Sub-station (Medina Addition)
|
This project is planned for a 24 month period.
|
$350,000
|
|
|
Design Ready
|
Construction of a building for a
dialysis center
(to be operated in Zapata by Doctor and Dialysis Company)
|
This project is planned for a 24 month period.
|
$1,500,000
|
|
|
Design Ready
|
Dock for San Ygnacio Bird Sanctuary (water fowl observation) and fishing dock
|
This project is planned for a 12 month period.
|
$150,000
|
|
|
Design Ready
|
US 83 Beautification and Enhancement Project in the Zapata community right of way
|
This project is planned for a 12 month period.
|
$500,000
|
|
|
Design Ready
|
Precinct 2 Miraflores Park in development in the underserved Medina Addition colonia
|
This project is planned for a 12 month period.
|
$250,000
|
|
|
Planning Ready
|
Airport Project Instrument Approach
(land acquisition and clearance easements)
|
This project is planned for a 24 month period.
|
$1,200,000
|
|
|
Planning Ready
|
Truck Traffic Relief Loop (will circumvent the community of Zapata--Texas Department of Transportation project; land acquisition and construction)
|
This project is planned for a 24 month period.
|
$10,000,000
|
|
|
|
Texas Department of Transportation Projects: Encourage the agency to complete designed project in county, i.e. Veleño Bridge, convert US 83 to 4-lane highway from Webb County line to community of Zapata, convert US 83 to 4-lane highway from community of Zapata to Starr County line
|
These projects are planned for 24 month periods each if funding becomes available. At least two projects could start within a 12 month period.
|
unavailable
|
|