Projects Coordinator
Mario Gonzalez-Davis
 
Phone: 956.765.9939
Fax: 956.765.9969
 
Physical Address
200 E. 7th Avenue
Zapata, TX 78076
 
Mailing Address:
P.O. Box 99
Zapata, TX 78076
  
 

 

Projects News

 

Representatives from the Office of Rural Community Affairs (ORCA) present a ceremonial oversized check to Zapata County officials for $500,000 to be used for sewer improvements in Falcon Lake Estates West. Project Coordinator Mario Gonzalez-Davis submitted the application on behalf of the county. (L-R) William Gudeman--Regional Director for ORCA, Zapata County Projects Coordinator Mario Gonzalez-Davis, Susan Grosz--Project Manager for ORCA's Community Development Division, Zapata County Judge Rosalva Guerra, and Zapata County Auditor Doroteo N. Garza.

posted: May 2008

 

 

Zapata County Museum bid opening scheduled for January 29, 2009 at 3 PM in McAllen at Project Management Innovations International, Inc. (PM2i) with construction mananger at risk Bobby Whatley.

posted: January 28, 2009

 

COMPLETED, ONGOING & UPCOMING 
ZAPATA COUNTY PROJECTS

Project Status

Proposed Project Description

Proposed Implementation Schedule

Project Cost

Project Image

Completed

Raw Water Intake Project

     2008 County Projects 026_sm

Completed

Airport Road Paving

     

Ongoing
(Quarter 1 2009)

Romeo T. Flores 
Park Project--Phase I

     2008 County Projects 015_sm
 Upcoming

Zapata County Higher Technology Center
Phase I

(adjacent to Zapata County Community Center)

     Tech Center 001_sm

Upcoming

Zapata County Boat Ramp Project
Phase I

     

 Ongoing

Zapata County Water Treatment Plant

     newwater1_web

Design & Planning complete; awaits funding

Zapata County Higher Technology Center
Phase II

The project is planned for a 24 month period

 $2,000,000

 

Design & Planning complete; awaits funding

Zapata County Museum
(old civic center site)

The project is planned for a 12 month period.

$3,500,00
County funds available: $1,800,00

 

Design & Planning complete; awaits funding

Zapata County Sewer Improvement
(Texas Water Development Board)

The project is planned for a 24 month period.

$6,400,000
County Texas Water Development loan

 

Design & Planning complete; awaits funding 

Las Palmas Colonia Sewer collection project 

The project is planned for a 24 month period. 

$1,700,000 

 

Design & Planning complete; awaits funding

School Safety Sidewalk project
Villarreal Elementary & South Elementary 

The project is planned for a 12 month period. 

$250,000

 

Design & Planning complete; awaits funding 

Storm Drainage 
Pct. 4 Park
(to maximize land use and control flooding)

The project is planned for an 18 month period. 

$750,000 

 

Design & Planning complete; awaits funding 

San Ygnacio 
Drainage Project
(project site is in and around the National Historic District--all Texas Historical Commission permits have been acquired.

The project is planned for an 18 month period. 

$1,500,000

 

Design & Planning complete; awaits funding

Flood Prevention in Medina Addition (colonia), as identified in the 2007 Flood Prevention Study

The project is planned for a 24 month period.

$6,500,000

 

Design & Planning complete; awaits funding 

County Boat Ramp Project--Phase II
(completion of presently designed park project--TXDOT administered project

This project is planned for a 24 month period. 

$1,500,000 

 

Design & Planning complete; awaits funding 

Jennings and Pedernales County Roads (drainage) 

The project is planned for a 12 month period. 

$600,000 

 

Design & Planning complete; awaits funding

Falcon Meza Colonia Paving Project

This project is planned for a 24 month period.

$2,300,000 

 

Design & Planning complete; awaits funding 

Veleño Bridge--utility relocation 
(required by Texas Department of Transportation) 

This project is planned for a 24 month period. 

$1,800,000
(paid by county) 

 

Design Ready

Paving of 
Aguilares Road FM 3169
(4.5 miles, from end of payment to county line; all easements are in place)

The project is planned for a 24 month period.

$5,400,000 

 

Design Ready

County Road 
Paving Project--
Jennings (10 miles), Pedernales (8 miles), 
Los Lobos (6 miles), Tepozan (.38 miles), Meza Salinas (4 miles), Alejandrenas (10 miles) 

This project is planned for a 48 months period. Work will be done in phases and could start in less than 12 months.

$38,380,000 

 

Design Ready 

Siesta Shore WCID, water distribution system
(renovation of inadequate distribution system, no fire protection) 

This project is planned for a 24 month period. 

$7,000,000 

 

Design Ready

Sheriff & Fire Department Sub-station (Medina Addition)

This project is planned for a 24 month period.

$350,000

 

Design Ready

Construction of a building for a 
dialysis center
(to be operated in Zapata by Doctor and Dialysis Company)

This project is planned for a 24 month period.

$1,500,000

 

Design Ready 

Dock for San Ygnacio Bird Sanctuary (water fowl observation) and fishing dock

This project is planned for a 12 month period.

$150,000

 

Design Ready

US 83 Beautification and Enhancement Project in the Zapata community right of way

This project is planned for a 12 month period.

$500,000

 

Design Ready 

Precinct 2 Miraflores Park in development in the underserved Medina Addition colonia

This project is planned for a 12 month period.

$250,000

 

Planning Ready

Airport Project Instrument Approach
(land acquisition and clearance easements) 

This project is planned for a 24 month period. 

$1,200,000 

 

Planning Ready

Truck Traffic Relief Loop (will circumvent the community of Zapata--Texas Department of Transportation project; land acquisition and construction) 

This project is planned for a 24 month period.

$10,000,000 

 

 

Texas Department of Transportation Projects: Encourage the agency to complete designed project in county, i.e. Veleño Bridge, convert US 83 to 4-lane highway from Webb County line to community of Zapata, convert US 83 to 4-lane highway from community of Zapata to Starr County line  

These projects are planned for 24 month periods each if funding  becomes available. At least two projects could start within a 12 month period. 

unavailable 

 

  

 
 Road Bond Paving  

Precinct #1

Precinct #2

Precinct #3

Precinct #4

       
Location:
Description:
Status:
Contractor:
Cost:
Scheduled Completion Date:
 
Location:
Description:
Status:
Contractor:
Cost:
Scheduled Completion Date:
 

Location:
Description:
Status:
Contractor:

Location:
Description:
Status:
Contractor:

 

 

 

 

 

 

 

 


Last updated: March 18, 2009